§ A.3.1.2 The Specifications:

(Either list the specifications here or refer to an exhibit attached to this Third Amendment.)

 See Exhibit 2

Section

Title

Date

Pages

 

§ A.3.1.3 The Drawings:

(Either list the drawings here or refer to an exhibit attached to this Third Amendment.)

See Exhibit 3

Number

Title

Date

 

§ A.3.1.4​The Sustainability Plan, if any:  - NOT USED.

(If the Owner identified a Sustainable Objective in the Owner’s Criteria, identify the document or documents that comprise the Sustainability Plan by title, date and number of pages, and include other identifying information. The Sustainability Plan identifies and describes the Sustainable Objective; the targeted Sustainable Measures; implementation strategies selected to achieve the Sustainable Measures; the Owner’s and Design-Builder’s roles and responsibilities associated with achieving the Sustainable Measures; the specific details about design reviews, testing or metrics to verify achievement of each Sustainable Measure; and the Sustainability Documentation required for the Project, as those terms are defined in Exhibit C to the Agreement.)

Title

Date

Pages

 None 

Other identifying information

None

§ A.3.1.5 Allowances and Contingencies:

(Identify any agreed upon allowances and contingencies, including a statement of their basis.)

.1     Allowances

Allowances, also identified as “Yet to Buy” costs, for various Scopes of Work are shown by work package or division.  See Exhibit 1 (dated March 1, 2019).

.2     Contingencies

Contingency is identified in Exhibit 1 (dated March 1, 2019)and is intended to be used by Design-Build Contractor as required to support project execution.   

§ A.3.1.6 Design-Builder’s assumptions and clarifications:

Client will be responsible for Commissioning of all building systems for both validated and non-validated systems. Commission, Qualification and Validation (CQV) requirements for all validated systems have not been provided to the design-build contractor and efforts to support those requirements are not included in this GMP .  Client agrees that assembly, execution and acceptance of all documentation and turn-over packages required to support commissioning efforts are within their scope. Design-Build contractor will provide labor, via subcontractors, to support execution of the clients commissioning efforts for non-validated systems.  

 